Saturday, December 18, 2010

Final walk through

We had our final walk through today with our on site manager!!!!! (Louie is great!!!) Anyway, I don't have 'final pictures' yet, but there have been some that have been taken since my last post that I will put on here.

We still have some things that need to be changed/fixed after walking through today. Touch up paint both interior and exterior. The pantry doors in the kitchen are the wrong type of door. Our master bathroom door doesn't match up with the latch where it closes. The master bathroom tub has a couple of cracks that they need to fix. Those are all somewhat minor things that will be taken care of on Monday.

Some of the larger items that still need done are: The window in the loft area needs to be Tempered glass, so that window needs to be replaced. They also need to add closed soffits per HOA that is required, and the landscaping is not complete due to weather. So a few larger things that are still in the works of being completed.

Otherwise it's looking really good, can't wait for the move in day!!!!!!!!!!!! Here are some more updated pictures, but still not final pictures!

Loft area
Laundry Room
Master Bath
Master Bath

Loft overlooking entry way

Kids play area under stairs
from living room looking into dining room

front stone pillars

Tuesday, December 7, 2010

Something new!

Alright, it's like we have had so many delays!!! I know I'm just antsy to get this house project completed! So we decided at the last possibly moment to have the interior living space painted :) Very happy we made that decision!

They have finished the prime and texture, now they are needing to paint the walls! yay! They started putting in the stair railing, and the molding around the base of the walls. They have put on some of the doors, and all the windows now have trim around them!!!!!!

OH MY GOSH it's so fun to see!!!!! After they paint the cabinets will go in and they are just days away from getting the carpet and vinyl on the floors! eeekkkk. Here are just a couple of pictures, we stopped by late tonight and it was dark so they didn't turn out super well. We will take more during the day for better lighting.

I LOVE that we chose to do railing all the way up and across the top of the stairway!!!!!!
Looking up from the front entry way
Looking at the front door from the living room/hallway
To the right is a 'powder room' bathroom
Another shot looking at the base of the stairs.
Our pile of cabinets sitting on the family room floor :)
We are told this portion of the building process goes incredably fast... lets keep our fingers crossed that it is true! Drew is hoping to be closing in 2 weeks~ me... I'm thinking after Xmas at this point! we shall see.